Chevron Corp.’s 50% owned affiliate, Tengizchevroil LLP (TCO), has commenced operations at its Wellhead Pressure Management Project (WPMP) at the Tengiz oil field in Kazakhstan.
TCO began operations by converting its first metering station at Tengiz to low pressure and activating the associated Pressure Boost Facility (PBF). This marks important progress for TCO’s overall expansion project at Tengiz.
The WPMP is designed to maintain the existing processing plants’ full capacity—approximately 28 million tonnes per annum (mtpa)—by lowering the flowing pressure at the wellheads and then boosting the pressure to the existing plants.
“This is a significant step towards completion of the Future Growth Project (FGP). It is also important progress for the modernization of the existing base business at Tengiz and demonstrates TCO’s commitment to safely and reliably manage operations, while maximizing the ultimate recovery of resources critical to global energy security,” said Clay Neff, president of Chevron International Exploration and Production.
The start-up of additional PBF compressors and the conversion of the remaining metering stations in the oil gathering system at Tengiz, from high pressure to low pressure, is scheduled for completion through the remainder of the year, the company said.
Future Growth Project, the final phase of TCO’s expansion project, is on track to conclude in the first half of 2025. TCO will be able to expand Tengiz crude oil production by an incremental 12 mtpa, or 260,000 bbl/d.
“This accomplishment highlights the vital role of partnership. Together with the Republic of Kazakhstan and our other partners, we have safely started operations at the WPMP, which is a positive development as we continue our focus on the FGP-WPMP expansion project,” said Derek Magness, managing director of Chevron’s Eurasia Business Unit.
Recommended Reading
US Appeals Court Upholds FERC Approvals for Gas Pipeline Expansion
2024-05-02 - A unanimous three-judge panel of the U.S. Circuit Court of Appeals for the D.C. Circuit held that the Federal Energy Regulatory Commission was right to determine the Evangeline Pass Expansion project is functionally separate from four related gas infrastructure developments.
Midstream Operators See Strong NGL Performance in Q4
2024-02-20 - Export demand drives a record fourth quarter as companies including Enterprise Products Partners, MPLX and Williams look to expand in the NGL market.
Williams Beats 2023 Expectations, Touts Natgas Infrastructure Additions
2024-02-14 - Williams to continue developing natural gas infrastructure in 2024 with growth capex expected to top $1.45 billion.
Enbridge Announces $500MM Investment in Gulf Coast Facilities
2024-03-06 - Enbridge’s 2024 budget will go primarily towards crude export and storage, advancing plans that see continued growth in power generated by natural gas.
Ozark Gas Transmission’s Pipeline Supply Access Project in Service
2024-04-18 - Black Bear Transmission’s subsidiary Ozark Gas Transmission placed its supply access project in service on April 8, providing increased gas supply reliability for Ozark shippers.