Energy Transfer on April 8 escalated its dispute over a Williams Cos. natural gas project, petitioning the Federal Energy Regulatory Commission (FERC) to determine whether the Louisiana Energy Gateway is an interstate pipeline developed without the commission’s approval.
“LEG looks like a transmission pipeline, will apparently operate like a transmission pipeline and its developer talks about it like it’s a transmission pipeline—but despite all that, Williams insists it’s a gathering line,” Dallas-based Energy Transfer contended in its 1,600-page filing.
The company also asks the regulator to decide whether a seven-factor test should be applied to determine whether Louisiana Energy Gateway is a gathering or transmission line as defined by the National Gas Act. A gathering line would not fall under FERC’s jurisdiction, but a transmission line would.
The 1.8-Bcf/d capacity project is designed to move natural gas from the Haynesville Shale to coastal Louisiana LNG export terminals beginning in 2025. The dispute with Energy Transfer has forced Williams to adjust its pipeline routes and push back its start date from fourth-quarter 2024.
“But we are pushing ahead and the project’s actually going fairly well,” Williams CEO Alan Armstrong told journalists last month at CERAWeek by S&P Global.
In a statement to Bloomberg, Williams said “Energy Transfer’s FERC complaint is another step by Energy Transfer to stifle competition in Louisiana. Williams looks forward to working with FERC on this matter.”
Energy Transfer co-CEO Thomas Long acknowledged during the company’s first-quarter earnings call with analysts that it had been accused of stifling competition by refusing right-of-way access on projects that would cross Energy Transfer’s pipelines. The company also seeks to expand its Gulf Run system to transport gas to LNG terminals.
Recommended Reading
TC Energy’s Keystone Back Online After Temporary Service Halt
2024-03-10 - As Canada’s pipeline network runs full, producers are anxious for the Trans Mountain Expansion to come online.
Enbridge Fortifies Dominant Role in Corpus Christi Crude Transport
2024-03-20 - Colin Gruending, Enbridge executive vice president and president for liquids pipelines told Hart Energy the company’s holdings in South Texas are akin to a “catcher’s mitt” for Permian and Haynesville production.
Enterprise Targets FID for SPOT Project by End of 2024
2024-05-01 - Enterprise Products Partners’ co-CEO disputed capex figures reported in the media regarding its Sea Port Oil Export Terminal.
Early Startup of Trans Mountain Pipeline Expansion Surprises Analysts
2024-04-04 - Analysts had expected the Trans Mountain Pipeline expansion to commence operations in June but the company said the system will begin shipping crude on May 1.
Kinder Morgan Sees Need for Another Permian NatGas Pipeline
2024-04-18 - Negative prices, tight capacity and upcoming demand are driving natural gas leaders at Kinder Morgan to think about more takeaway capacity.