U.S. energy firm Equitrans Midstream delayed the estimated completion of its Mountain Valley natural gas pipeline from West Virginia to Virginia to the second quarter from the first quarter due in part to adverse weather in January.
The company also boosted the projected cost to complete the project to around $7.57 billion-$7.63 billion, up from a prior estimate of about $7.2 billion.
Equitrans spoke about Mountain Valley in its fourth earnings report, which beat estimates.
Mountain Valley is the only big gas pipeline under construction in the U.S. Northeast. It has encountered numerous regulatory and court fights that have stopped work several times since construction began in 2018.
The pipe, which is key to unlocking gas supplies from Appalachia, the nation's biggest shale gas-producing region, needed a bill from the U.S. Congress that was signed into law by the president and help from the Supreme Court before it could restart construction.
In its earnings release, Equitrans CEO Diana Charletta said "construction crews encountered adverse weather conditions, including precipitation well above 20-year averages."
"These conditions were far worse and longer in duration than anticipated, imposing a significant impact on productivity, which, in turn, impeded our ability to reduce construction headcount," Charletta said.
Delays and cost overruns are nothing new for Mountain Valley.
When Mountain Valley started construction in February 2018, Equitrans estimated the 2 Bcf/d project would cost about $3.5 billion and enter service by late 2018.
The 303-mile (488-kilometre) Mountain Valley project is owned by units of Equitrans, the lead partner building the pipe with a roughly 49% interest, NextEra Energy, Consolidated Edison, AltaGas and RGC Resources. Equitrans will operate the pipeline.
Separately, Equitrans Executive Chairman Thomas Karam said in the earnings release that the "Board of Directors has been engaged in a process with third parties that have expressed interest in strategic transactions with our company."
He said the board has engaged outside advisors and the process is ongoing, noting "There is no guarantee that any transaction will result from this process."
Recommended Reading
NAPE: Chevron’s Chris Powers Talks Traditional Oil, Gas Role in CCUS
2024-02-12 - Policy, innovation and partnership are among the areas needed to help grow the emerging CCUS sector, a Chevron executive said.
Sangomar FPSO Arrives Offshore Senegal
2024-02-13 - Woodside’s Sangomar Field on track to start production in mid-2024.
CNOOC Makes 100 MMton Oilfield Discovery in Bohai Sea
2024-03-18 - CNOOC said the Qinhuangdao 27-3 oilfield has been tested to produce approximately 742 bbl/d of oil from a single well.
TPH: Lower 48 to Shed Rigs Through 3Q Before Gas Plays Rebound
2024-03-13 - TPH&Co. analysis shows the Permian Basin will lose rigs near term, but as activity in gassy plays ticks up later this year, the Permian may be headed towards muted activity into 2025.
Proven Volumes at Aramco’s Jafurah Field Jump on New Booking Approach
2024-02-27 - Aramco’s addition of 15 Tcf of gas and 2 Bbbl of condensate brings Jafurah’s proven reserves up to 229 Tcf of gas and 75 Bbbl of condensate.